Rise to Power test



 Rise to power tests started in September 1999, and reactor power was increased step-by-step to 10MW, to 20MW and then finally to 30MW. Full power of 30MW-thermal and reactor outlet coolant temperature of 850°C was achieved in December 2001. Certificate of pre-operation test, that is, operation permit of the HTTR was issued in March 2002.The HTTR accomplished the maximum reactor outlet coolant temperature of 950°C in April 2004 in high temperature test operation. Operation permit for the high temperature test operation was issued in June 2004.